• Greenacre project jdg
  • Greenacre project jdg
Location
Greenacre NSW
Contract Value
350 K
Date
-
Project Overview
Cable installation works at the Greenacre Substation 410V, 11kV & 132kV

Full Details

JDG Civil was contracted to undertake cable installation works at the Greenacre Substation, plus variations to the contract including time critical construction of conduit system around road closures. 

Multiple sizes of 132kV cable installed, from joint bays outside of substation we installed Taihan into the substation and also installed Prysmian 132kV 1C400sq Cu XLPE.

We pride ourselves on the ability to self-perform entire projects. 

The tasks we self-perform include but not limited to:
  1. Complete Project and Site Management
  2. Excavation and construction of cable duct lines
  3. Non-destructive excavation
  4. Power Cable installation ranging from 240V to 330kV (Low Voltage to Extra High Voltage)
  5. Bulk Excavation
  6. Trenching
  7. Directional Drilling / Underboring
  8. Concrete construction
  9. Saw cutting
  10. Spoil removal and disposal
  11. Traffic management services
  12. As Built’s
  13. Use of GPS Equipment